Contract No.: | DC/2018/07 |
Contract Title: | Shek Wu Hui Effluent Polishing Plant -
Main Works Stage 1 - Civil Works for Sewage Treatment Facilities |
Date of Award: | 5 November 2019 |
Contractor: | KL-CW JV |
Date of Commencement: | 18 November 2019 |
Anticipated Date of Completion: | 26 March 2024 |
Awarded Contract Sum: | HK$ 952,409,600.00 |
Scope of Works: | The works include Civil works for Sewage Treatment Facilities including Inlet Works No. 1, Primary Sedimentation Tanks No. 1 - 4, Bioreactor No. 2A & 2B, Membrane Facilities Building No. 2, SAS Pumping Station, auxiliary facilities (temporary chemical dosing system, concrete plinth for deodorisation systems, chemical systems no. 1 and no. 2, FS and sprinkler pumping room, emergency generator house, street fire hydrant pump room and flowmeter chambers) and the associated works |
Contact Us
Mailing Address:
SWHEPP AECOM CRE Project Office,
260 Castle Peak Road,
San Tin, New Territories,
Hong Kong
Tel: (852) 9721 1172
Fax: (852) 3907 6199
SWHEPP AECOM CRE Project Office,
260 Castle Peak Road,
San Tin, New Territories,
Hong Kong