SWHEPP
SWHEPP
  • What‘s New
  • SWHEPP
    • SWHEPP
    • - Existing SWHSTW
    • - Need for Improvement Scheme
  • Expansion Works & Assessment
    • Assessment
      • Assessment
      • - Preliminary Technical Assessment of Relocation
      • - Improvement Option
      • - Environmental Impact Assessment
      • - Traffic Impact Assessment
    • Expansion Works
      • Expansion Works
      • - Combined Scheme of Expansion Works
      • - Improved SWHEPP
      • - Main Works Stage 1 Progress and Timetable
  • Sustainable Development
    • Sustainable Development
    • - Sewage and Sludge Treatment
    • - Architectural and Landscape Design
    • - Odour Control
    • - Energy Efficiency
  • Environmental Monitoring & Audit
  • Public Consultation
    • Public Consultation
    • - Past Activities
    • - Report on Public Consultations in Investigation Stage
    • - Opinion Collection Form
  • Information Centre
    • Information Centre
    • - Newsletter and Digest
    • - FAQ
    • - Related Links
  • Main Works Stage 1
    • Main Works Stage 1
    • - Project Information
    • - Work Progress Photo
    • - Project Features
    • - Environmental Monitoring Data
    • - Awards
    • - Enquiries & Contact Us
  • Contact Us

Font Size / Print / 繁 简

Expansion Works  

After completion of SWHEPP expansion Works, its treatment capacity will be increased to 190,000 m3/day. The combined scheme of expansion works will be implemented in phases, as follows:

  • Advance Works: Commenced in mid 2015 and designed to increase the treatment capacity by 12,000 m3/day.
  • Main Work Stage 1: Commenced on 11 September 2019 to increase the treatment capacity by 35,000m3/day.
  • Remaining Stages: To provide additional capacity of 50,000m3/day.

To cope with other large scale development in the future, the need for new effluent polishing plants will be investigated by other Department.


Contact Us

Shoud you have any enquiry, please feel free to contact us.

Mailing Address:
SWHEPP AECOM CRE Project Office,
260 Castle Peak Road,
San Tin, New Territories,
Hong Kong

Tel: (852) 9721 1172
Fax: (852) 3907 6199

enquiry@SWHSTW.hk


Shek Wu Hui Sewage Treatment Works
Sustainable Development and Environmental Monitoring & Audit
Information Centre
Contact Us

Address (Mailing):

SWHEPP AECOM CRE Project Office,
260 Castle Peak Road,
San Tin, New Territories,
Hong Kong

  • Accessibility Statement
  • Importance Notice
  • Privacy Policy
Copyright 2021 © Drainage Services Department. | Last review date: 20 July 2021